US Army Corps of Engineers

Green Peter Dam

Friday February 16, 2018

HourTotal Outflow cfsGeneration Flow cfsSpill cfsForebay ElevationTailwater ElevationAverage Head
1 50 951.40 692.10 259.30
2 50 951.43 692.10 259.33
3 50 951.45 692.10 259.35
4 50 951.47 692.11 259.36
5 50 951.50 692.10 259.40
6 50 951.52 692.11 259.41
7 50 951.54 692.11 259.43
8 50 951.58 692.10 259.48
9 50 951.60 692.11 259.49
10 50 951.63 692.10 259.53
11 50 951.65 692.10 259.55
12 50 951.68 692.11 259.57
13 50 951.71 692.11 259.60
14 50 951.73 692.11 259.62
15 50 951.76 692.11 259.65
16 50 951.78 692.11 259.67
17 50 951.81 692.10 259.71
18 50 951.83 692.09 259.74
19 50 951.86 692.10 259.76
20 50 951.89 692.11 259.78
21 50 951.93 692.10 259.83
22 50 951.96 692.17 259.79
23 50 951.99 692.18 259.81
24 50 952.02 692.18 259.84
AVG 50   951.70 692.11 259.58
MAX 50   952.02 692.18 259.84
MIN 50   951.40 692.09 259.30