US Army Corps of Engineers

Rocky Reach Dam

Monday June 24, 2019

New Date:

HourTotal Outflow kcfsGeneration Flow kcfsSpill kcfsForebay ElevationTailwater ElevationAverage Head
1 76.90 70.30 6.30 706.16 615.38 90.78
2 86.70 82.10 4.30 706.04 616.83 89.21
3 117.20 112.60 4.30 706.00 617.25 88.75
4 111.50 106.80 4.40 705.97 617.21 88.76
5 113.60 109.00 4.30 705.81 616.58 89.23
6 88.00 83.40 4.30 705.57 615.71 89.86
7 88.20 83.50 4.40 705.21 615.84 89.37
8 102.60 96.00 6.30 705.31 616.82 88.49
9 120.60 113.20 7.10 705.26 617.67 87.59
10 134.80 126.10 8.50 705.11 618.11 87.00
11 117.90 109.20 8.50 705.10 617.34 87.76
12
13
14
15
16
17
18
19
20
21
22
23
24
AVG 105.27 99.29 5.70 705.59 616.79 88.80
MAX 134.80 126.10 8.50 706.16 618.11 90.78
MIN 76.90 70.30 4.30 705.10 615.38 87.00