US Army Corps of Engineers

Dexter Dam

Thursday July 10, 2025

New Date:

HourTotal Outflow cfsGeneration Flow cfsSpill cfsForebay ElevationTailwater ElevationAverage Head
1 2058 693.01 637.73 55.28
2 2086 692.89 637.74 55.15
3 2058 692.78 637.74 55.04
4 2044 692.68 637.76 54.92
5 2058 692.56 637.74 54.82
6 2058 692.44 637.74 54.70
7 2044 692.34 637.72 54.62
8 2044 692.23 637.75 54.48
9 2044 692.12 637.76 54.36
10 2072 692.00 637.76 54.24
11 2086 691.89 637.76 54.13
12 2044 691.78 637.74 54.04
13 2044 691.66 637.75 53.91
14 2086 691.55 637.74 53.81
15 2072 691.44 637.76 53.68
16 2058 691.58 637.77 53.81
17 2058 691.73 637.76 53.97
18 2058 691.88 637.76 54.12
19 2086 692.28 637.76 54.52
20 2072 692.69 637.75 54.94
21 2072 693.10 637.77 55.33
22 2072 693.25 637.73 55.52
23 2058 693.14 637.75 55.39
24 2086 693.02 637.73 55.29
AVG 2063   692.34 637.75 54.59
MAX 2086   693.25 637.77 55.52
MIN 2044   691.44 637.72 53.68