John Day Dam
Saturday September 7, 2024
Hour | Total Outflow kcfs | Generation Flow kcfs | Spill kcfs | Forebay Elevation | Tailwater Elevation | Average Head |
1 | 67.00 | 56.20 | 9.90 | 264.62 | 158.92 | 105.70 |
2 | 69.10 | 56.50 | 9.90 | 264.62 | 158.82 | 105.80 |
3 | 69.00 | 56.50 | 9.90 | 264.62 | 158.92 | 105.70 |
4 | 67.10 | 56.30 | 9.90 | 264.72 | 158.92 | 105.80 |
5 | 68.60 | 56.00 | 9.90 | 264.83 | 158.92 | 105.91 |
6 | 66.90 | 56.20 | 9.90 | 264.73 | 159.02 | 105.71 |
7 | 76.40 | 64.80 | 10.70 | 264.62 | 159.32 | 105.30 |
8 | 76.50 | 64.20 | 11.40 | 264.62 | 159.12 | 105.50 |
9 | 76.90 | 64.60 | 11.40 | 264.62 | 159.22 | 105.40 |
10 | 76.90 | 64.50 | 11.40 | 264.72 | 159.32 | 105.40 |
11 | 79.00 | 64.90 | 11.40 | 264.72 | 159.42 | 105.30 |
12 | 77.30 | 64.90 | 11.40 | 264.62 | 159.22 | 105.40 |
13 | 78.90 | 64.70 | 11.40 | 264.62 | 159.52 | 105.10 |
14 | 79.90 | 65.70 | 11.40 | 264.52 | 159.92 | 104.60 |
15 | 91.20 | 78.80 | 11.40 | 264.52 | 159.72 | 104.80 |
16 | 93.10 | 80.80 | 11.40 | 264.52 | 160.02 | 104.50 |
17 | 109.60 | 97.20 | 11.40 | 264.52 | 160.22 | 104.30 |
18 | 111.70 | 99.40 | 11.40 | 264.73 | 160.19 | 104.54 |
19 | 110.20 | 97.80 | 11.40 | 264.82 | 160.12 | 104.70 |
20 | 110.20 | 97.80 | 11.40 | 264.72 | 160.12 | 104.60 |
21 | 103.90 | 91.50 | 11.40 | 264.72 | 159.92 | 104.80 |
22 | 101.90 | 89.30 | 9.90 | 264.73 | 159.92 | 104.81 |
23 | 71.60 | 60.90 | 9.90 | 264.82 | 159.22 | 105.60 |
24 | 73.10 | 62.40 | 9.90 | 264.93 | 159.72 | 105.21 |
|
AVG | 83.58 | 71.33 | 10.81 | 264.68 | 159.49 | 105.19 |
|
MAX | 111.70 | 99.40 | 11.40 | 264.93 | 160.22 | 105.91 |
MIN | 66.90 | 56.00 | 9.90 | 264.52 | 158.82 | 104.30 |